Site inspections are required at a number of different stages
which follow the general construction process.
Building work will need to be inspected at the following
stages:
- Commencement
- Excavation of Foundations and/or Trial Holes
- Oversite (the hardcore materials before oversite concrete is
laid)
- Drains in place prior to backfilling
- Drains backfilled and placed on test ready for inspection
- Occupation
- Completion
Additional inspections are also undertaken dependent upon the
scale and complexity of the building work proposed. These include,
but are not restricted to:
- First Floor Level
- Roof Construction
- Sound Insulation
- Thermal Insulation to walls/ashlars and first floors where
relevant
- Roof Insulation
- Structural Beams/Frames
- Fire Protection to walls, floors and beams where relevant
Inspections can be requested using the Online Request a Building Control Inspection
Form or by contacting your area surveyor or the
office on 01233 330282.
Inspection requests made by 10am will be carried out on
the same day. If you require a timed visit then you are advised to
speak to the surveyor directly.
This webpage was updated on 9/15/2008