Loft Conversions
This webpage gives general guidance on the requirements relating
to loft conversions. This guide assumes an attached, two-storey
house, with a new second floor loft room. If your property differs
from this example, you should seek further advice.
Note: certain requirements will not be imposed on bungalows with
a loft room. More onerous requirements will be applied to three
storey buildings with loft rooms.
Smoke Detection
Detectors should be interlinked, mains powered with battery
backup, and be installed on all three levels. Generally, detectors
should be positioned over the head of the stair, on each landing.
Further details on smoke detection can be obtained from our guide
on smoke detection or from the Kent Fire Safety Service.
Fire Break Walls and Sound Insulation
In the loft there should be walls separating a property from any
adjacent property. This wall both prevents fire spreading between
properties and also gives sound insulation. Even if an existing
wall separates properties, it may need to be upgraded to give
adequate sound insulation. Two possible methods are:
- Two independent stud walls, with 100mm mineral fibre between
and two layers of 12.5mm plasterboard each side.
- Dense concrete blocks laid as a cavity or solid wall. Even if
the existing wall is solid masonry, it may need to be upgraded.
Usually the heavier and denser the wall the better sound insulation
provided. Sound insulation can be undermined if joints around
bricks or blocks are not completely filled with mortar. Also, holes
cut for electrical boxes etc. educe the thickness of the masonry
and so reduce sound insulation.
Air Gap Insulation
A minimum of a 50mm air gap is needed over any insulation. This
is to prevent a build up of condensation. Condensation encourages
rot and reduces the effectiveness of insulation. A 50mm air gap and
a through flow of air should prevent this. A through flow of air
must be provided by eaves ventilation the equivalent of a
continuous 25mm strip, and ridge ventilation the equivalent of a
continuous 5mm strip. The ventilation strip must also have a screen
to stop insects from entering the roof. Care should be taken with
the type of ventilation strip used. Strips usually are slotted to
hold the fly screen in place. This means that a 50mm wide slotted
strip will need to be used to be equivalent of a continuous 25mm
wide strip. When insulation is installed, care must be taken to
make sure the free flow of air is not blocked. The eaves of the
existing roof may already have some ventilation. This must be
checked, as it may need to be increased to achieve the
requirement.
Room Ventilation
Room ventilation is required to all habitable rooms. This is to
prevent and remove unpleasant living conditions. To this end, the
following must be provided:
- An openable window area equal to 1/20th of the floor area be
provided as rapid ventilation
- Background ventilation equal to 8000mm²
- Bathrooms require mechanical extraction at least equal to 15
litres/second.
Headroom
There is no requirement regarding headroom in loft rooms (except
to stairs and landings).However, headroom should be carefully
considered. Floor joist sizes, allowances for deflection, decking
thickness, battening of rafters, plasterboard thickness all have an
effect on the overall headroom within the loft room. This may make
the new loft room unusable when complete.
Stairs
Stairs must have the rise (r) and going (g) relationship (2r +
g) which must be between 550mm and 700mm. The maximum pitch for a
stair is 42 degrees. Headroom on a stair and landings must be at
least 2m, this can be reduced on stairs to 1.9m at the centre and
1.8m at the outside edge (but not landings). There is no minimum
stair width, but a stair less than 600mm wide will be difficult to
negotiate, particularly with furniture. Handrails on the stair
should be between 900mm and 1100mm above the pitch line. Balusters
should not allow a 100mm sphere to pass through and must not be
readily climbable by children.
Glass and Glazing
Any glazing on the escape route (generally, not external
windows, wc's or bathrooms) must be half hour fire resisting)
normally Georgian wired glass is suitable) and must be installed
with a beading system compatible with the glass used. Any glazing
(both internally and externally) including doors and windows in
certain critical locations (typically low level, adjacent or in
doors), must be toughened and/or be of safety glazing.
Completion Certificates
At the end of a satisfactory job, you will receive a Building
Regulations completion certificate. Usually this is issued directly
to the homeowner, or to the builder to present to the homeowner
along with the final account. With either method, it is very
important the completion certificate is issued. This certificate
not only demonstrates that the work complies with all current
Building Regulations, but also will be required in a future
property sale.
© Pat Bale IMIBC, GIFireE, 1999
See the Design and
Fire Safety webpages
also.
This webpage was updated on 3/7/2008