Ashford.gov.uk
 
  Home > Planning and Building Control > Building Control > Technical Guidance > Loft Conversions
Loft Conversions

This webpage gives general guidance on the requirements relating to loft conversions. This guide assumes an attached, two-storey house, with a new second floor loft room. If your property differs from this example, you should seek further advice.

 

Note: certain requirements will not be imposed on bungalows with a loft room. More onerous requirements will be applied to three storey buildings with loft rooms.

Smoke Detection

Detectors should be interlinked, mains powered with battery backup, and be installed on all three levels. Generally, detectors should be positioned over the head of the stair, on each landing. Further details on smoke detection can be obtained from our guide on smoke detection or from the Kent Fire Safety Service.

Fire Break Walls and Sound Insulation

In the loft there should be walls separating a property from any adjacent property. This wall both prevents fire spreading between properties and also gives sound insulation. Even if an existing wall separates properties, it may need to be upgraded to give adequate sound insulation. Two possible methods are:

Air Gap Insulation

A minimum of a 50mm air gap is needed over any insulation. This is to prevent a build up of condensation. Condensation encourages rot and reduces the effectiveness of insulation. A 50mm air gap and a through flow of air should prevent this. A through flow of air must be provided by eaves ventilation the equivalent of a continuous 25mm strip, and ridge ventilation the equivalent of a continuous 5mm strip. The ventilation strip must also have a screen to stop insects from entering the roof. Care should be taken with the type of ventilation strip used. Strips usually are slotted to hold the fly screen in place. This means that a 50mm wide slotted strip will need to be used to be equivalent of a continuous 25mm wide strip. When insulation is installed, care must be taken to make sure the free flow of air is not blocked. The eaves of the existing roof may already have some ventilation. This must be checked, as it may need to be increased to achieve the requirement.

Room Ventilation

Room ventilation is required to all habitable rooms. This is to prevent and remove unpleasant living conditions. To this end, the following must be provided:

Headroom

There is no requirement regarding headroom in loft rooms (except to stairs and landings).However, headroom should be carefully considered. Floor joist sizes, allowances for deflection, decking thickness, battening of rafters, plasterboard thickness all have an effect on the overall headroom within the loft room. This may make the new loft room unusable when complete.

Stairs

Stairs must have the rise (r) and going (g) relationship (2r + g) which must be between 550mm and 700mm. The maximum pitch for a stair is 42 degrees. Headroom on a stair and landings must be at least 2m, this can be reduced on stairs to 1.9m at the centre and 1.8m at the outside edge (but not landings). There is no minimum stair width, but a stair less than 600mm wide will be difficult to negotiate, particularly with furniture. Handrails on the stair should be between 900mm and 1100mm above the pitch line. Balusters should not allow a 100mm sphere to pass through and must not be readily climbable by children.

Glass and Glazing

Any glazing on the escape route (generally, not external windows, wc's or bathrooms) must be half hour fire resisting) normally Georgian wired glass is suitable) and must be installed with a beading system compatible with the glass used. Any glazing (both internally and externally) including doors and windows in certain critical locations (typically low level, adjacent or in doors), must be toughened and/or be of safety glazing.

Completion Certificates

At the end of a satisfactory job, you will receive a Building Regulations completion certificate. Usually this is issued directly to the homeowner, or to the builder to present to the homeowner along with the final account. With either method, it is very important the completion certificate is issued. This certificate not only demonstrates that the work complies with all current Building Regulations, but also will be required in a future property sale.

 

© Pat Bale IMIBC, GIFireE, 1999

 

See the Design and Fire Safety webpages also.

| Help Using the Website |

This webpage was updated on 3/7/2008

A to Z of Services

A B C D E F G H I J K L M N O P Q R S T U V W X Y Z
Beacon Council
Directgov, public services all in one place
Advanced Search
Ashford Borough Council, Civic Centre
Tannery Lane, Ashford TN23 1PL
Telephone: 01233 331111
Email: customer.care@ashford.gov.uk or view our Compliments and Complaints webpage.
Ashford Borough Council Ashford, Best Placed in Britain